Home :: Academic Members :: News

view:41878   Last Update: 2022-5-17

Seyed Hadi Hosseini

Research Projectes

Project Title Responsibility Start Date End Date Kind of Project Commander Availibility
high current transformers of Kimia petrochemical maintenance management    LeaderSeptember 2011September  2015
online oil purification of power transformerin Farabi petrochemical co.   LeaderNovember 2015November  2015
designing and manufacturing 750kV transformer for high voltage laboratory of university of tehran   ColleagueOctober 2000June  2001Tavanir organization
feasibilty of using 765 kV in IRAN power grid   ColleagueOctober 2002June  2004Tavanir organization
Hormozgan electrical region stability studies   ColleagueJune 2001June  2002Tavanir organization
redesigning and repairing of moving coil transformer   LeaderMarch 2011February  2012lya special material co.
designing, manufacturing and trest of high current bushing transformer for glass furnace    LeaderJune 2010October  2010lya special material co.
substation expansion planning for sistan & balochestan until 2022   LeaderMarch 2013In ProgressSistan & balochestan electrical region
sub transmission substation expansion planning for khozestan electrical region until 2025   Leader_APRIL 2012_AUGUST  2014khozestan electrical region
optimum placement of subtransmission substations in north, south and razavi khorasan   LeaderMarch 2008July  2008khorasan electrical region co., moniran

 

 

Copyright © 2024, University of Zanjan, Zanjan, Iran
master[at]znu.ac.ir